A.L. Miller Village-Monthly Construction update #2

Construction activities have been under way for approximately 7 to 8 weeks. Work has been concentrated on Building 1 but foundation work has started on the single family homes. Significant progress has been made at Building 1 and we anticipate that the new roofing systems will be installed in the near future. Demolition and abatement work will commence at Building 2 in the immediate future as well.


If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.
For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.

Demolition started at Building 2 gymnasium:

Sheathing removed from windows:

Unit framing under way or complete at 12 units in Building 1:

Clean‐up and demolition nearly complete at Building 1:


One foundation started at single‐family lots: