Tuesday, February 9, 2016

A.L. Miller Village-Monthly Construction update #3

Work is progressing well and is now under way at Buildings 1, 2, 3 and the single-family component of the project. Significant progress has been made at Building 1 and we expect most of the window glazing and MEP rough-in work will be completed in the next 4-6 weeks. Demolition and abatement work will continue at Building 2 for the next several weeks and rough framing may commence prior to our the end of next month. We also anticipate the remaining foundation and slabs will be complete at the single-family component and rough framing will continue there, as well.

If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  

For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.


Framing substantially complete at Lot #9:

Four foundations and under-slab plumbing complete at single-family lots:

Second-floor framing remains at units in former auditorium:

Unit framing 80-85% complete at Building 1:

Demolition complete at fire damaged Gymnasium:

Building 2 sealed off as abatement work is under way: