A.L. Miller Village-Monthly Construction update #7

In Building 1, Progress is most complete at the east wing where all of the MEP rough-in, plaster repairs, interior window framing and insulation work is complete. The next area of progress is at the west wing where the majority of MEP rough-in work has been completed with the exception of the HVAC rough-in which was nearing completion. Plaster repairs and interior window framing work are underway and cover-up inspections should be completed within the next 30 days. Progress at the north wing has continued as the under-slab plumbing work has been completed and the slab pour backs are complete. Rough framing work has also been completed and plumbing rough-in was nearing completion. Drywall installation has been completed along party walls and areas where rated assemblies are required prior to installation of tubs and tying-in of interior wall partitions. The tile and terrazzo floors have been cleaned throughout the building and rough sanding of the hardwood floors had been completed. At the building exterior, pressure washing and cleaning of the brick and cast stone veneer was completed over the past period.

At Building 2, Cutting of thru-wall passages was found to be complete and concrete slab cutting and demolition work has been completed. At the interior of the building, unit framing is estimated to be 85-90% complete and installation under-slab plumbing is 90% complete and the slab pour back has been completed at the two-story section of the building. 

Construction of the single-family residential units continues to progress. Siding, soffit and exterior trims have been completed at 4 units and driveway installation is also complete at 3 units. MEP rough-in is now substantially complete at all 9 units and insulation and drywall has been completed at 4 units. Interior door installation and the prime coat of paint is now complete at 4 units, as well.


If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  

For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.


Building 1 pressure washed:

Plaster repairs completed at each wing of Building 1:

Brick, siding and exterior trims complete at 4 single-family units:

Drywall, paint prime and door installation complete at 4 single-family units:

Insulation completed at east wing of Building 1:

Waste and water rough-in underway at Building 2: