Tuesday, July 19, 2016

A.L. Miller Village-Monthly Construction update #8

At Building 1, rough framing and re-glazing work is considered to be substantially complete and rough-in of the MEP systems remains in progress. Construction within Building 1 has been isolated into building sections which include the east wing, west wing and north/south wing. Progress is most complete at the east wing where all of the MEP rough-in, plaster repairs, interior window framing and insulation work is complete and drywall installation and finishing is now underway. The next area of progress is at the west wing where the majority of MEP rough-in work has been completed at the 2nd and 3rd floors and is nearly complete at the 1st floor. Lastly, progress at the north/south wing has continued. Under-slab plumbing, slab pour backs and rough framing work is now complete. Plumbing and fire sprinkler rough-in is estimated to be 90 to 95% complete, HVAC rough-in 30% complete and electrical rough-in 20% complete at the north/south wings. Drywall installation has been completed along party walls and areas where rated assemblies are required prior to installation of tubs and tying-in of interior wall partitions throughout Building A; pre-drywall work is now substantially complete. The tile and terrazzo floors have been cleaned throughout the building and rough sanding of the hardwood floors had been completed. At the building exterior, pressure washing and cleaning of the brick and cast stone veneer was completed over the past period and concrete refinishing was noted to be in progress at exterior stair systems leading from the auditorium area. The elevator jack bore was also completed.

At Building 2, cutting of thru-wall passages was found to be complete and concrete slab cutting and demolition work has been completed. At the interior of the building, unit framing is estimated to be 90% complete and installation of under-slab plumbing is now complete. Slab pour backs were recently completed at the one-story section of the building and slab repairs are now complete. Additionally, above slab waste and water rough-in is estimated to be 75% complete. At the exterior of the building, re-glazing of the existing windows was found to be mostly complete and installation of the new roofing system is mostly complete.

On the Single-Family Units,f oundations, concrete slabs, rough framing, roofing, house wrap, exterior windows and doors, brick veneer, driveways and sidewalks are now complete at each unit. Siding, soffit and exterior trims have been completed at 6 units. MEP rough-in, insulation and drywall is now complete at all 9 units. Unit finishes at lots 1-4 are nearing completion as interior doors and trim, floor coverings, cabinetry, small appliances and MEP trim-out work is complete. Interior painting was estimated to be 90% complete and miscellaneous finishes such as shelving, door hardware, bath hardware and blinds were noted to be in place.

If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  

For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.


Pressure washing completed at Building 1:

Parking lot construction underway at north side of Building 1:

Stucco repairs underway at stairs from auditorium at Building 1:

Drywall finishing in progress at units on east wing of Building 1:

Gutter installation underway at Building 2:

Unit framing 90% complete at Building 2:

Floor coverings complete at 4 single-family units:

Cabinets and small appliances installed at all 4 single-family units:

Driveways complete at all single-family units: