Wednesday, November 23, 2016

A.L. Miller Village-Monthly Construction update #11

Construction has been completed at the 9 single family homes!

At Building 1, rough framing, re-glazing of the original window frames and MEP rough-in work is substantially complete.  Installation of wall insulation is mostly complete and finishes are now underway at each section of the building. The tile and terrazzo floors have been cleaned throughout the building and rough sanding of the hardwood floors has been completed. Plaster repairs have also continued to progress and are 90% complete. At the building exterior, pressure washing and cleaning of the brick and cast stone veneer and masonry repairs at stair systems are complete. Construction of the elevator shaft continus to progress and the CMU work is considered to be complete. 

At Building 2, trash out, interior demolition, asbestos abatement, lead paint encapsulation and smoke sealing has been completed. Cutting of thru-wall passages, concrete slab cutting, coring and demolition work has also been completed. At the interior of the building, rough framing, drywall pre-hang, plumbing rough-in and sprinkler rough-in work is complete. HVAC rough-in was estimated to be 45% complete and electrical rough-in was approximately 90% complete. At the exterior of the building, roofing and gutter installation are substantially complete and re-glazing of the original windows is nearly complete.

At the Gymnasium, trash out, interior demolition, asbestos abatement, lead paint encapsulation, roofing and re-glazing have been completed.


If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  

For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.


Landscaping completed at single-family lots:

 Single-family homes complete!

 Masonry finish and railings repaired at auditorium egress steps:

 CMU work complete at elevator shaft/equipment room:

 Finishes progressing at east wing of Building 1:

 Drywall installation and finishing nearing completion at west wing of Building 1:

 MEP rough remains in progress at Building 2: