At Building 2, rough framing and drywall pre‐hang work are now complete and MEP rough‐in work is complete along the south end of the 2‐story portion of the building. MEP rough‐in work has continued along the north half of the building and the west single‐story wing. HVAC rough‐in is 75 to 80% complete and fire sprinkler rough‐in is around 85% complete. At the exterior of the building, roofing and gutter installation is substantially complete and re‐glazing of the original windows is nearly complete.
Interior finishes at Building 2, will start soon and drywall stocking had already commenced in this section of the building.
If you have any questions or would like to send us a comment regarding A.L. Miller Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com. Please use this email for questions or comments regarding the development process only.
For information regarding pre-leasing, please email almiller@fairwaymanagement.com or call 478.744.2455.
CMU and wood framing complete at elevator shaft/corridor extension:
Stucco repairs nearly complete at Building 1:
Re‐glazing work complete at Building 1:
Cabinets and paint prime complete at east wing:
Lighting fixtures and HVAC trim mostly complete at east wing:
Drywall mostly complete at west wing and interior door installation under way:
Exterior glazing mostly complete at Building 2:
MEP rough‐in nearly complete at south wing of 2‐story section at Building 2:
CMU and wood framing complete at elevator shaft/corridor extension:
Stucco repairs nearly complete at Building 1:
Re‐glazing work complete at Building 1:
Cabinets and paint prime complete at east wing:
Lighting fixtures and HVAC trim mostly complete at east wing:
Drywall mostly complete at west wing and interior door installation under way:
Exterior glazing mostly complete at Building 2:
MEP rough‐in nearly complete at south wing of 2‐story section at Building 2: